Abstract:On the basis of the study of crossfault mobile deformation monitoring environment in the Capital Region of China, it is found that there are a few sites(near 20%) impacted by the nonseismic factors. So we suggest that the crustal deformation monitoring techniques(instruments) and the crossfault deformation surveying line layout should be improved and the crossfault flow deformation level ling survey and baseline level of observation should be at the same pile. The baseline survey pile of existing level and baseline measurements should be technologically transformed at the appropriate time,in the measurement instrumentation: DiNi electronic level should be used instead of Ni002 Optical Level, Di2002 even TC2003 and TCA series of instruments should be used instead of the 24m traditional foot baseline deformation monitoring.
Lu Mingyong,Liu Tianhai,Huang Baosen et al. DISCUSSION OF ENVIRONMENT AND MONITORING TECHNOLOGYFOR CROSS-FAULT MOBILE DEFORMATION MONITORING[J]. jgg, 2011, 31(5): 141-145.